Ward 2 Phase II Project

Print

Project Start Date:  June 8, 2015
Scheduled Completion Date: October 1, 2015
Contractor:  Martam Construction
Site Contact:  Bruce Stone, Robinson Engineering 708-514-4934

As of June  26, 2015
Construction activities have slowed due to high water levels of the creek and subsequent water table.  Work is planning to resume on June 30th.

 

Week of June 8, 2015
Martam Construction has begun the removal trees for the installation of the Water Main.